Garage build

Fall front to back (1:40??) The dimensions are 8m x 6m, as im 1m away fom boundary the roof has to be under 2500 so trusses are a no go sadly.
 
Slow progress atm as been waiting for steel - got to wait when its coming for free. Building inspector specified 203x133 overkill maybe but it knocks the price down by half for the joists by splitting the span. My back is knackered at the mo so waiting for that to sort itself out but should be making progress real soon as need the roof on before winter kicks in

6.5m x 203x133 ready to go
20160907_080132.webp
 
Rsj is up - me and my mate who i train with just lifted it in place. Only 200kg easy :D20160926_182225.webp
Trench part dug for wiring will be finished tomorrow (its actually over a spade deep but does not look it in the pics for some reason)
20160926_182212.webp 20160926_182202.webp
Ordered the 7x2 joists/wall plate/joist hangers etc and they will be here in the morning. Get the joists up within the next week soon have it watertight - got the paslode nail gun ready for action
 
Afternoon on the roof today got half of the joists on, get it finished tomorrow hopefully if weather is ok. Took ages to drill the 13mm holes for the m12 coach bolts to bolt the timber in the webbing into the rsj - it was like bell metal rock hard. Knacked 3 drill bits even with cutting fluid when i started it last week so bought a drill bit sharpener for the job which worked awesome:D

20161008_164952.webp 20161008_165006.webp
 
Trusses ?? No trusses on this roof mate ;) joists only. The joists are stitched in to wallplate/timber in the webbing with 6x 90mm paslode nails each end / joist hangers which is a more than acceptable way of doing it. Only ever seen diy'ers screw them down sadly not proper tradesman:D

624 twist nails later in the joist hangers and we are somewhere near:D get the noggins boshed in and fascia on next week then board it. Not a bad job steady away.

20161009_172724.webp 20161009_183604.webp
 
If you weren't such a massive fucking hulk i'd bash you one for that :D

Haha thats what you get for mocking my nailing skills - time served joiner here:D roofing a piece of piss compared to when i was on the bench making counters and double winder staircase
 
Last edited by a moderator:
Slow progress but getting there slowly

Fascias on
20161204_160430.webpRoof pic
20161204_150309.webp
Drive is getting there. 56 ton of gear out
20161112_075107.webp 20161120_132137.webp
Ripped the shitty rotten ranch style dividing fence down and fitted a close boarded one in its place20161126_133445.webp
20161126_133456.webp
Blocks going down. 6000 blocks to the front door - probably 9000 ish in total 156sqm

20161204_141852.webp
20161204_141909.webp
New wall - over enthusiastic grab truck took the old one20161210_130403.webp 20161210_130412.webp 20161210_130411.webp 20161210_130438.webp

Drive will be done next week hopefully. I have 3 weeks off work no so have the materials on order for the roof covering - see if the weather plays ball and we may have a watertight garage before the end of the year :D
 